What does seasonal testing look like and how does that work in regards to Envelope Cx.
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium forForum discussion
NC-v4 EAc1: Enhanced commissioning
What does seasonal testing look like and how does that work in regards to Envelope Cx.
LEEDuser is supported by our premium members, not by advertisers.
Go premium forTo post a comment, you need to register for a LEEDuser Basic membership (free) or login to your existing profile.
Scott Bowman
LEED FellowIntegrated Design + Energy Advisors, LLC
LEEDuser Expert
519 thumbs up
March 15, 2018 - 1:12 pm
I will speak to the general question. Seasonal testing related to systems which only function during certain weather conditions. The easiest would be a heating system where you need a heating load to really allow functional testing of systems. You can test some responses based on inputs or other means, but you need cold weather to really test some sequences.
With EnvelopeCx, and I have asked a real expert to respond, it would be more related to conditions where a test can be done. The example I can think of is thermal scans. If IR scans are part of a testing plan, you need a large differential temperature to get good images. So you might want to wait until a very cold period and then test at night to get really good contrast to see where there may be problems.
Elizabeth Cassin
Associate Principal and Unit ManagerWiss, Janney, Elstner
LEEDuser Expert
18 thumbs up
March 15, 2018 - 11:12 pm
Seasonal testing of a building enclosure is for any system or component whose operation is dependent on the season or when the test depends on weather conditions and is deferred. Examples of a "seasonal facade" include automated ventilation or solar control systems...usually dynamic/active systems that can be tied into the building's BAS. Not that common in most buildings, but you may run into it in some very high performing enclosures. Examples of a "seasonal test" include IR scans and whole building air tightness testing.
Sue Bryant
engineerNoresco
9 thumbs up
October 22, 2019 - 2:26 pm
For option 1, requiring seasonal testing and a 10 month review, does the project need to wait 10 months after completion in order to be able to submit this credit? Or is there a way to submit, say, a CxA contract detailing that these steps will be performed?
Gustavo De las Heras Izquierdo
LEED Expert181 thumbs up
October 23, 2019 - 7:29 am
Hi Sue,
That is a very common issue in LEED projects. We usually include a comment in the Final Cx Report saying that seasonal testing is pending and the Commissioning Agent will perform deferred testing.
Sue Bryant
engineerNoresco
9 thumbs up
October 23, 2019 - 5:25 pm
Excellent, thank you Gustavo.
Sara BENLOUBA
Green building managerConfidential
12 thumbs up
November 30, 2020 - 5:05 am
hello Dears,
We have appointed a facade / curtain wall company for our project and we intend to entrust it with the mission of carrying out the necessary tests concerning the commissioning of the envelope. At the same time, we have a Commissioning Authority for earning (4 points of LEED commissioning).
Would it be acceptable from a LEED point of view for the tests to be carried out by the company of execution of facade but on condition that these tests are supervised and verified by our principal commissioning Authority. In other words, is this envelope commissioning testing must be conducted only by commissioning authority and cannot be accepted if conducted by execution company of facade but supervised, verified and approved by commissioning authority?