I am working on EB Project in LEED V4. In V4 the advance sub-metering is required 1. Chilled water System: Chiller and Chilled water pumps 2. Condenser Water Pumps: Cooling tower, Condenser water pumps 3. Air Handling unit- Supply fans, return fan, damper motor i just want to know that each air handling unit have separate electrical meter or one meter for all Air handling unit. also, want to know that if HVAC Have a single meter having AHU, PUMP, Cooling tower and Chiller then can i eligible to take this credit.