I have a client that would like to install charging stations for SS 4.3 Option 2 compliance. How do you demonstrate vehicle fueling capacity per station when each electric vehicle charges at a different rate?
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
David Posada
Integrated Design & LEED SpecialistSERA Architects
LEEDuser Expert
1980 thumbs up
April 14, 2011 - 12:27 pm
Not sure if I understand your question - the credit requirements are only looking at "capacity" as the number of parking spaces, and providing 3% of that number of spaces as ones reserved for fueling or charging alternative fuel vehicles. We don't need to provide info about the rate or capacity of power being provided - except that actual charging equipment does need to be installed (not just 120 V outlets) Does that answer your question?
Alicja Bieszyńska
Skanska114 thumbs up
December 5, 2011 - 3:15 am
In LEED v3 the reference guide sais "prepare information about the number of fueling stations provided, the alternative fuel station type, manufacturer, model number, and the fueling capacity per station" (documentation guidance).
In LEED CS v2.0 it sais even more: "confirm the fuel type, number of stations, and fueling capacity for each station for an 8-hour period".
So I guess we need to specify the power of charging equipment. As far as I am concerned, different electric vehicles need different plugs and voltage...
Any idea how detailed the specification needs to be?
Thanks!
Lauren Wallace
LEED Project Reviewer, LEED AP BD+C, Senior LEED SpecialistCertifications Department Manager, Epsten Group, Inc.
39 thumbs up
January 6, 2012 - 12:15 pm
Hi, Alicja!
If you install 240 volt charging stations, then the assumption is that you are offering what is considered a "rapid charge," and that an electric car could fully charge in at least 8 hours. As far as documentation goes, you would need to show the number and location of the refueling/recharging stations, as well as the specifications for the type of station being provided (with the intent of proving that you are providing at least 240 volt outlets). Hope that helps!