Schools-2009 EAc1:Optimize Energy Performance

EA Cr-1 - Process Energy Cost less than 25%

Project K-12 school, The enegry calculation done for the entire building but the process enegry cost comes less than 25%. What is the next step should I provide the supporting documents (Narrative) in the tempete is good enough?

4

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Fri, 08/12/2011 - 15:38

You will need to provide a narrative and ideally supporting calculations to demonstrate the actual projected plug loads. Most often a spreadsheet is provided with a room-by-room calculation of this load.