I may have missed this but, what does the project team input in the template if there is no extraction data provided from the manufacturer but they have the manufacturing distance and wish to apply that product for the manufacturering portion of the credit? Do you have to supply distances for materials that you are not counting toward the credit but show up in the template because you applied them in the recycled content credit that is linked? The same lack of extraction data question applies to this instance as well.

3

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Fri, 09/09/2011 - 14:32

We simply enter 501 miles and had never had a problem with it. Problem solved.

Mon, 09/12/2011 - 12:53

Thanks! I will advise my contractor to do this for our current project.

Add new comment

To post a comment, you need to register for a LEEDuser Basic membership (free) or login to your existing profile.