Hi I know accessories are included but are actual plumbing fixtures included in these calcs? They are not with Divs 3-10
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium forForum discussion
NC-2009 MRc4: Recycled Content
Hi I know accessories are included but are actual plumbing fixtures included in these calcs? They are not with Divs 3-10
LEEDuser is supported by our premium members, not by advertisers.
Go premium forTo post a comment, you need to register for a LEEDuser Basic membership (free) or login to your existing profile.
The recycled content percentage on the product data sheet is given as a range. What should I do?
Is the default average recycled content value of 25% for steel still allowed?
Can site materials, such as soil, be included in the MR credit calculations?
Are there recycled content claims that I should be wary of?
RETIRED
LEEDuser Expert
623 thumbs up
January 23, 2015 - 5:00 pm
Erika - You answered your own question - since plumbing fixtures are not specified in the Divisions outlined for the MR credits (Divisions 03-10 and the required sections in 31 and 32), they are NOT included in the calculations. In addition, the credit requirements specifically say: "Mechanical, electrical and plumbing components, and specialty items such as elevators and equipment cannot be included in all calculations."
Erika Duran
Sustainability ConsultantDagher Engineering
72 thumbs up
January 23, 2015 - 4:56 pm
Thank ya, thank ya