I'm working on a shopping center development that will include at time of occupancy more than 10 diverse uses within project boundary. May we count this uses to comply with the bicycle network requirement ("bicycle network that connects to at least 10 diverses uses")?
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
Marilyn Specht
Vice President & Managing Principal, US SustainabilityIntroba
LEEDuser Expert
51 thumbs up
January 17, 2017 - 2:56 pm
Hi Pedro, I recommend you confirm with GBCI directly. Under v2009 there was a limit to how many services you could count within your project boundary and I believe that is the case for v4 as well. But perhaps walking GBCI through your specific project and how you meet the credit intent might be helpful context.