How are the FTE and PTE numbers derived? The project is for a surgical addition.

Do I use actaul FTE and PTE numbers provide by the Owner?

Or are the numbers based on the square footage of the space and the actual or design occupant loads?

The 2nd floor is future fit-out space as well as part of the project. Does this fall under the category of Medical Office per Table 1 - LEED C&S 2009- Appendix 1?

On Table PLF3-1:
I have listed 3 types of spaces:
1) Surgical---->Healthcare: Inpatient
2) Circulation/Mechanical ----->Circulation Space (this includes the 4th floor mechanical space, which I listed as un-conditioned)
Is this the correct way to list mechanical space?
3) Future Fit-out Space (2nd Floor)
What space type usage should be listed? It will not let me select the "other" category.

How is the regularly occupied area calculated? The only real occupied space is the 3rd floor, which consists of 4 OR rooms, (2) scrub rooms, some storgage rooms, telcom room, sterile cooridor and a circulation corridor around the periphery of the entire floor.

Surgeries go on around the clock with people coming and going, but no one really occupies the 3rd floor on a full time basis.

Thanks.