Forum discussion

Design review appeal

We have been denied a prerequisite from the Design Phase after the second review, and now we need to appeal them or start with the construction review. We have two main questions: Do we have any timeline for appealing? Is it correct to fix it during the construction review? Thankyou

0

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Thu, 06/06/2013 - 13:41

It depends on which prerequisite has been denied. If the one denied is at all related to other credits in the construction phase then you should appeal before submitting the construction credits. If not related then it you could do it concurrently. There is not definitive timeline for submitting an appeal.

Add new comment

To post a comment, you need to register for a LEEDuser Basic membership (free) or login to your existing profile.