Assume a building to be demolished has large HVAC equipment and electrical gear, etc., and is not being reused but discarded. How would these be included and documented in CWM tracking? Would these be included? I have not encountered this issue before and would appreciate any thoughts. Thanks!
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
Renee Shirey
Stantec422 thumbs up
March 6, 2018 - 10:16 am
It is part of the demolition waste, and should be treated like all other demo waste. The only waste that wouldn't be tracked from a demolition would be the removal of hazardous/toxic items (asbestos, etc), and those would be removed before the 'typical' demolition of a building. If the equipment is going to a recycler/scrap yard, then you need documentation like any other haul to a recycler. If the equipment is going to a landfill (I hope not), then you need documentation like any other haul to a landfill.