FAQs about EAp2 :

Can the Passive House Planning Package (PHPP) be used to energy model for LEED?

Is it acceptable to model a split-type AC with inverter technology compressor as a heat pump, like modeling VRF?

Can the Trace 700 'LEED Energy Performance Summary Report' by uploaded to LEED Online in lieu of the Section 1.4 tables spreadsheet?

A portion of our building envelope is historic. Can we exclude it from our model?

Which baseline HVAC system do I use if my building has no heating or air conditioning?

For an existing building, do I need to rotate the model?

Our project has a diesel backup generator. Should we include it in our energy model?

Our project has a large process load—75%. Despite our efforts to make an efficient HVAC design, the cost savings are minimal. What can we do to earn this prerequisite and be eligible for LEED certification? Is there any flexibility in how we model the p

Can SHGC be higher in the proposed than in the baseline model?

Our process load is higher than 25%. Do we have to justify that?

Do I need to justify the electrical and fuel rates I am using in my model?

Our local code references ASHRAE 90.1-2010. Should I use that for my documentation, or 90.1-2007?

Can I claim exterior lighting savings for canopy lighting even though a baseline model cannot include shading elements?

The project is built on a site with existing exterior lighting installed. How should this be accounted for?

Can mezzanines open to floors below be excluded from the energy model?

How do I provide a zip code for an international location?

For a project outside the U.S., how do I determine the climate zone?

For a project outside the U.S., how do I determine the Target Finder score?

Do hotel rooms need automatic light shut-off control?

How commonly are the 90.1 mandatory compliance forms submitted as part of EAp2/EAc1?

View answers »

Forum discussion

NC-2009 EAp2:Minimum Energy Performance

Demand Control Ventilation

Hi, I am wondering what savings can be taken by using room occupancy controls to control the HVAC system in a 24/7 building. 1) Technically the system can setback when not in use, but I am not sure whether this can be incorporated. 2) Also the system uses the occupancy controls for demand controlled ventilation, is it adequate to make an assessment of when the rooms will be occupied and only provide ventilation during those time (whilst the baseline with have ventilation 24/7)? Thanks

0

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Wed, 09/21/2016 - 18:08

Dear Victoria, IMO: Short answer is yes, you can take credit for DCV. But it depends a bit on how the control loop works. I might not be understanding your question, but this may help: - Occupancy profiles/schedules must be the same for baseline and proposed - Setback control schedules must be the same in proposed and baseline. 1)Yes, but setback must be incorporated in baseline too. In general, take credit for reduced OA ventilation rates not for ON/OFF AC. If AC is off in proposed, it should be off in the baseline. Again, this might not be the case for your specific control loop. 2)Yes, if your building is occupied 24/7 I would model a constant ventilation rate 24/7 for baseline. but if you are taking credit for demand control ventilation in the proposed, then you should model ASHRAE 62.1 minimum ventilation rates from IEQp1 for Baseline systems.

Fri, 09/23/2016 - 14:17

See the Advanced Energy Modeling Guide for LEED (one of the appendicies) for an example applied to a hotel room occupancy sensor.