Hi all,
We re currently working on an office building project of 10.000 square meters and within the building there is a data center as big as 150 square meters.
we are plannig to apply v2009 NC. we have made the energy modelling for the building and the calculations of the data center has decreased our energy points a great deal.
What i'd like to know is that, are the data centers within a new constaction building modeled with the same baseline values of the NC or not, since their energy consumptions are fairly high.
Thank you!'
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
Marcus Sheffer
LEED Fellow7group / Energy Opportunities
LEEDuser Expert
5909 thumbs up
December 22, 2014 - 10:52 am
This is a process load and must be included in both models identically.
There is a spreadsheet you can use to show energy savings associated with a data center.
http://www.usgbc.org/resources/minimum-energy-performance-data-center-ca...
ESRA OZKONUKSEVER
MA. ArchitectILTAY MIMARLIK
5 thumbs up
January 23, 2015 - 9:36 am
bit late to thank you but you are a great help thanks!'