For all the equipment or products which qualify as best management practices (paints ,cleaning equipment etc) and are highlighted in the plan,do we need to provide cut sheets for the submission?
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
Jason Franken
Sustainability ProfessionalLEEDuser Expert
608 thumbs up
August 17, 2010 - 10:45 am
No, you are not required to provide any manufacturer documentation along with the finished Plan for SSc2, although you may do so if you would like to highlight that you are using compliant products at least 20% of the time.