CS-2009 IEQp1:Minimum IAQ Performance

C&S scope

We are working on a C&S project but in the middle of the design phase we learned that a gym will lease three floors. Air handling units will be installed on all floors except in the gym. The gym will install their own AHU´s. Do we need to include the ASHRAE ventilation requirements in the lease agreement?

5

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Thu, 05/19/2011 - 15:14

ASHRAE 62.1 compliance is required for any space in the building. So yes, if the owner is not installing the ventilation system as part of the C&S than the lease agreement needs to require the gym to comply with ASHRAE.