Greetings, In the project I'm modeling (C&S), I took the opportunity to use the CS 2009 EAp2-c1 ACP spreadsheet with integrated calculator. I've come to reach 46% of Energy cost influenced by CS Owner. The spreadsheet (together with the necessary explanations) could be uploaded in EAp2 and also in EAc1 form upon ACP section. The question is: How to enter the revised points (for example 7 instead of 5). I don't see such place on the forms. The same question is also for the renewable energy, because it should also be influenced by the same percentage. Thanks.