FAQs about EAp2 :

For a project outside the U.S., how do I determine the Target Finder score?

Do hotel rooms need automatic light shut-off control?

How commonly are the 90.1 mandatory compliance forms submitted as part of EAp2/EAc1?

The Section 9 space-by-space method does not include residential space types. What should I use?

Can the Passive House Planning Package (PHPP) be used to energy model for LEED?

Is it acceptable to model a split-type AC with inverter technology compressor as a heat pump, like modeling VRF?

Can the Trace 700 'LEED Energy Performance Summary Report' by uploaded to LEED Online in lieu of the Section 1.4 tables spreadsheet?

A portion of our building envelope is historic. Can we exclude it from our model?

Which baseline HVAC system do I use if my building has no heating or air conditioning?

For an existing building, do I need to rotate the model?

Our project has a diesel backup generator. Should we include it in our energy model?

Our project has a large process load—75%. Despite our efforts to make an efficient HVAC design, the cost savings are minimal. What can we do to earn this prerequisite and be eligible for LEED certification? Is there any flexibility in how we model the p

Can SHGC be higher in the proposed than in the baseline model?

Our process load is higher than 25%. Do we have to justify that?

Do I need to justify the electrical and fuel rates I am using in my model?

Our local code references ASHRAE 90.1-2010. Should I use that for my documentation, or 90.1-2007?

Can I claim exterior lighting savings for canopy lighting even though a baseline model cannot include shading elements?

The project is built on a site with existing exterior lighting installed. How should this be accounted for?

Can mezzanines open to floors below be excluded from the energy model?

How do I provide a zip code for an international location?

View answers »

Forum discussion

NC-2009 EAp2:Minimum Energy Performance

Continuous insulation on the inside of the wall?

Our state energy code is based on ASHRAE 90.1-2004, which I believe does not require ci for exterior walls. ASHRAE 90.1-2007 requires R-3.8 ci for nonresidential walls. The project architect designed to the current code, but the project is registered in LEED 2009, so we need to meet the 2007 mandatory provisions for the envelope, including the ci layer. Unfortunately, the structure has been built, but the interior drywall has not been placed. Do you think we could be considered to meet the 90.1-2007 mandatory provision if we put an R-3.8 layer on the inside, under the drywall? We would still have thermal bridging through the ceiling / floor joists, but would break the thermal bridge from all of the studs on both first and second floors.

1

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Tue, 04/24/2012 - 15:32

Hey Dave, The insulation levels in 90.1 are not mandatory so you are not required to meet them for LEED. Not meeting them will potentially affect your savings but perhaps you can make that up in other areas. 90.1 prescriptively requires continuous insulation but it is up to the designers to determine where is goes.

Tue, 04/24/2012 - 16:18

EAp2 reads "Comply with the mandatory provisions (Sections 5.4, 6.4..." And 90.1-2007 Section 5.4 seems to say to me that our insulation must comply with the "requirements found in Sections 5.8.1.1 through 5.8.1.9." And that seems to prescribe a layer of R-3.8 in the wall section. Or does the insulation column offer one way to meet the Assembly Maximum U value? But I could meet it another way (higher R insulation between the studs, for instance)?

Tue, 04/24/2012 - 17:37

Sections 5.8.1.1 to 5.8.1.9 deal with the insulation material and in some cases the installation of that insulation. I don't see any section that requires continuous insulation. Which section in particular has you thinking it is prescribed? Unfortunately this does not get simpler, the reality is actually more complex. Note that the insulation values in Tables 5.5-1 to 5.5-8 are the prescriptive requirements, they are not mandatory. You could demonstrate prescriptive compliance by exceeding the overall U-value indicated in the tables. So the answer to your last question is yes but you are required to determine the overall U-value, not a point calculation. The U-values in these tables and the U-value of your proposed envelope assemblies is calculated according to 90.1 Appendix A. So for example a steel stud wall overall U-value must be calculated (and modeled) using table A3.3 to account for the thermal bridging in the wall assembly. So a 6 inch steel stud wall at 16" OC with no continuous insulation with R19 batts has an overall U-value of 0.109 (R9.2). All envelope assembly U-values must be calculated and modeled according to Appendix A.

Tue, 04/24/2012 - 17:42

My bad. I was looking at Table 5.5-5 and interpreting the R requirements to be mandatory. Thanks for your patience. And thank you for clarifying the task of calculating U values.

Tue, 04/24/2012 - 18:07

No problem, you aren't the first to have issues understanding 90.1! Fun stuff eh . . .

Add new comment

To post a comment, you need to register for a LEEDuser Basic membership (free) or login to your existing profile.