SSc4 requires the survey to be conducted either (1) each day over 5 consecutive workdays) or (2) at the conclusion of 5 consecutive workdays.

Our project wants Option #2 (on Friday for the end of a M-F workweek), but this excludes many people who telecommute or have a compressed workweek. Would it be okay to conduct the survey on a Wednesday, for the previous 5 workdays? (Ex: Conduct survey on W 7/23, for dates T 7/22, M 7/21, F 7/18, and Th 7/17).