Hi , We are working on Mega project is Saudi Arabia where we are using the concrete waste to build Safety road/excavation barriers which will be used on site during construction instead of purchasing new barriers. They will be moved out of site and utilized in another project after the project completion. Can they contribute toward MR CR2
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
Saud Abdul Rasheed
Sustainability/Energy Engineer, CEM, PMP, LEED AP BD+C, LEED AP O+M, Estidama PQP23 thumbs up
November 29, 2016 - 9:05 am
Dear Ahmad,
Yes if the concrete waste will be used somewhere else on another project then it is a technique to divert it from landfill which is the intent of the credit. You will need to track and document the waste.