Wed, 12/08/2010 - 18:42

George, for purposes of MRc2, the credit requires only diverting and tracking waste from the project site itself. You asked about your Construction Waste Management Plan, which does not have to address waste produced off-site, however, if your company wants to encourage responsible waste management from your vendors beyond the credit requirements, you can voluntarily opt to include it in your CWM plan. Just be sure any off-site waste figures are not factored into your LEED credit form tabulations.

Thu, 12/09/2010 - 08:11

Thanks Valerie! That was helpful!