I've filled this entire form out checking "in scope" for the first section, "zero CFC refrigerants" for the second section and a narrative that reads "Each new rooftop (Daikin RPE) are factory shipped and pre-charged with R-407C. There are no other pieces of HVAC equipment using refrigerant for this new base building project."
However, the EA Prerequisite 3: Fundamental Refrigerant Management
Precertification Compliance Documented: still shows "N" in the box.
What else do I need to do? Please help.
Mike Barker
Principal : Energy / Electrical EngineerBuildingPhysics South Africa
150 thumbs up
March 19, 2015 - 8:03 am
Yep, seems that little bug is still around ...
I made use of the "Special Circumstances" text box to document my problem and to then draw their attention to it. Hope that will be acceptable ?