hii, We are doing LEED - CI project, I am getting what should I submit at design stage, I can submit copy of contract, google survey and a draft M&V plan. Is this will meet the credit requirement because a final report that is mentioned in check list can be submitted after one year. So if I submit only draft M&V plan will this be sufficient??
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
Marcus Sheffer
LEED Fellow7group / Energy Opportunities
LEEDuser Expert
5912 thumbs up
July 1, 2011 - 9:00 am
When submitting fior the credit the M&V Plan should not be a draft, it should be final.
I am not sure how this fits in a CI project since you are not required to do an energy model? This pilot credit requires you to follow Option D, which requires the calibration of an energy model. I am not saying you can't do it, just that it is very unusualy for a CI project to pursue this credit.
monu goyal
Environmental EngineerMetadesign Architects Pvt. Ltd.
51 thumbs up
July 2, 2011 - 1:32 am
this pilot credit is also applicable for CI projects, and also we are doing Energy simulation for our project space in the building. So if I am doing Energy simulation what I have to complete M&V plan, and can I submit this credit in design stage or have to wait for completion of the project.??
Marcus Sheffer
LEED Fellow7group / Energy Opportunities
LEEDuser Expert
5912 thumbs up
July 2, 2011 - 9:32 am
In LEED 2009 this is usually considered a construction credit to be submitted with your construction submission. In your case, since you are not submitting the energy model for any other credit, I don't see why you couldn't submit it with your design credits.