Could anyone confirm that CI v3 projects registered after 04/08/2016 using the Alternative Compliance Path described in LEED Interpretation 10412 (tenant-level energy simulation) must earn at least 4 points to document prerequisite compliance, hence achieving a minimum of 10% instead of 6% improvement over baseline building. Thank you.
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
Marcus Sheffer
LEED Fellow7group / Energy Opportunities
LEEDuser Expert
5907 thumbs up
May 9, 2018 - 3:55 pm
Yes CI v3 projects registered after April 8, 2016 must meet these requirements.
Charalampos Giannikopoulos
Senior Sustainability ConsultantDCarbon
84 thumbs up
May 13, 2018 - 12:29 pm
Thank you.