FAQs about EAp2 :

For a project outside the U.S., how do I determine the Target Finder score?

Do hotel rooms need automatic light shut-off control?

How commonly are the 90.1 mandatory compliance forms submitted as part of EAp2/EAc1?

The Section 9 space-by-space method does not include residential space types. What should I use?

Can the Passive House Planning Package (PHPP) be used to energy model for LEED?

Is it acceptable to model a split-type AC with inverter technology compressor as a heat pump, like modeling VRF?

Can the Trace 700 'LEED Energy Performance Summary Report' by uploaded to LEED Online in lieu of the Section 1.4 tables spreadsheet?

A portion of our building envelope is historic. Can we exclude it from our model?

Which baseline HVAC system do I use if my building has no heating or air conditioning?

For an existing building, do I need to rotate the model?

Our project has a diesel backup generator. Should we include it in our energy model?

Our project has a large process load—75%. Despite our efforts to make an efficient HVAC design, the cost savings are minimal. What can we do to earn this prerequisite and be eligible for LEED certification? Is there any flexibility in how we model the p

Can SHGC be higher in the proposed than in the baseline model?

Our process load is higher than 25%. Do we have to justify that?

Do I need to justify the electrical and fuel rates I am using in my model?

Our local code references ASHRAE 90.1-2010. Should I use that for my documentation, or 90.1-2007?

Can I claim exterior lighting savings for canopy lighting even though a baseline model cannot include shading elements?

The project is built on a site with existing exterior lighting installed. How should this be accounted for?

Can mezzanines open to floors below be excluded from the energy model?

How do I provide a zip code for an international location?

View answers »

Forum discussion

NC-2009 EAp2:Minimum Energy Performance

Central Chilled Water Plant

We are investigating how a building which houses a central chilled water plant for a campus can meet the prerequisite. This building houses the chillers and cooling towers plus some electrical equipment. There is an occupied control room and a couple of other spaces which will be fully conditioned by separate HVAC systems. It will not use any of the chilled water it generates. Our interpretation is that the DES guidance does not apply since the building is not served by the DES. The chilled water plant therefore becomes a process load and any savings would have to be demonstrated following the exceptional calcualtion method. Any thoughts? Has anyone heard of a stand-alone central plant building obtaining LEED certification? If so any insight on how they did the modeling to meet the minimum requirements?

2

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Thu, 03/31/2011 - 19:42

Did you see this comment yet? http://www.leeduser.com/credit/NC-2009/EAc1?page=1#comment-8802 I am currently working on a similar project. First make sure you can get 1 FTE.

Thu, 03/31/2011 - 20:32

Interesting. There was an old CIR EAc1 Ruling dated 10/6/06 and the questions was "should the electricity used to create chilled water for the buildings other than the central plant be accounted for in the EA credit 1 calculation for the central plant building?" Ruling was "No. Although the language in ASHRAE/IESNA 90.1-2004 may suggest including the entire chiller capacity as a process load when modeling the plant building, such an interpretation is ambiguous and in any case that method is inappropriate for LEED purposes. When calculating process energy use for a central chiller plant building’s energy model, include only the percentage of the chiller plant capacity that is consumed within the central plant building itself." In our case the central plant building will not use any of the chilled water output, so we felt it did not apply. If the central plant building does use some of the outout from the plant then I think the DES requirements kick in. In our case, I don't think it does.

Mon, 06/23/2014 - 18:08

Marcus, Did you confirm the correct approach? I have a project with the exact same situation and would love to know the outcome. Thanks,

Mon, 06/23/2014 - 18:24

The project did not happen so we stopped looking into it. Anyone else do one of these projects?

Mon, 06/23/2014 - 21:00

We have modeled manufacturing facilities in which there is a Central Utiltiy Building (CUB) onsite that houses the boilers/chillers/cooling towers. On one project we looked into certifying the CUB. The GBCI response to this same question was: For a central plant building, the energy consumption utilized to generate thermal energy (i.e., chilled water or hot water) for use in buildings outside the LEED Project Boundary does not need to be considered within the energy models for EAp2: Minimum Energy Performance. However, any heat gains from the central plant equipment, and the impact of these loads on the local heating and cooling systems of the central plant, must be accounted for within the models. Hope this helps.

Mon, 06/23/2014 - 21:21

We received similar guidance on our Hospital Campus project. We posed the question to the GBCI during the design phase so that we could incorporate the utility plant properly into energy models.

Add new comment

To post a comment, you need to register for a LEEDuser Basic membership (free) or login to your existing profile.