All,

We are working on a unique facility (production greenhouse) which based on my understanding of EA Pre1 Cr2 can only meet this prerequisite using Case 2 options B--historical data and C- benchmarking; as it does not meet the requirements under Option A generic benchmark of Other.

We have gathered appropriate benchmarking data, but as the facility is part of a campus, in which sub-meters were not originally installed when the project was built 3 1/2 years ago we do not have 3 years of historical building data.

Subsequently sub-meters have been installed, and we have 1 1/2 years of building energy data, we also have 3 + years of campus wide historical data. However it looks as if we need three years of historical building specific energy data in order to fill out portion B of the Case 2 Calculator, and cannot use part C unless we have B finished.

Is there precedent for using only benchmarking data when historical data is not available? Has anyone ever encountered similar issues and developed solutions that GBCI/USGBC will accept? I seem to recall precedents in previous O&M version CIRs that exempted historical data if sub-meters were installed.

Thanks for any insights!

Marc