Our project has hit a bit of a wall and need some guidance on updating credit forms after submitting for review.
The project is going for a split review and we prepared all the design credits to be submitted and subsequently clicked submit for review. However, at this time the project was put on hold due to a major design change. As a result, payment for design review was never made. Since the project's design has changed so much we need to update all the credit forms, but obviously this can't be done because LOv3 is saying that the credits are under review. But the review process hasn't started since payment has not been made.
Is there a way to reverse/cancel our review stage so we can go back and edit the credit forms?
Would appreciate any insight you guys may be able to provide.
Thank you.
Tristan Roberts
RepresentativeVermont House of Representatives
LEEDuser Expert
11478 thumbs up
January 16, 2013 - 10:04 pm
Nathan, I would contact GBCI and ask for help with this. I'm sure they'll oblige.
Kerrie Schueffner
LEED SpecialistUSGBC
8 thumbs up
January 17, 2013 - 11:04 am
We would be happy to take a look at the project in our system, and adjust the project review status as needed. We'll contact you through email to resolve this. Thank you!
Kerrie Schueffner
LEED SpecialistUSGBC
8 thumbs up
January 17, 2013 - 1:16 pm
For others interested or for those that may have similar situations, please note that because the review for the project that Nathan has described has not yet started, it makes it easier to adjust the project status as there is nothing to re-review. However, please note that adjusting the project review status may not be appropriate for all phases of review and in all instances, especially if credit reviews have substantively commenced, and fees/payments are still subject to the policies outlined in the current Certification Policy Manual: https://www.leedonline.com/irj/go/km/docs/documents/usgbc/leed/config/te....
Nathan Lee
Project EngineerSGS Korea
56 thumbs up
January 20, 2013 - 7:21 pm
Kerrie, thank you so much for your assistance on this.
The Project Name is registered as: Parnas Tower. Please let me know if there is any other information that you require.
Thank you again!
Nivedietha RajKumar
June 28, 2024 - 11:29 am
I forgot to Submit Project Information for Design Submission in Leed Online is there a problem?