Dear LEED experts
I have a doubt that wheater a project can earn this credits if only rainwater reuse system is used in the project, no permeable paving, rain gardedn and other infiltrate measures.
Forum discussion
EBOM-v4.1 SSc1: Rainwater Management
Dear LEED experts
I have a doubt that wheater a project can earn this credits if only rainwater reuse system is used in the project, no permeable paving, rain gardedn and other infiltrate measures.
LEEDuser is supported by our premium members, not by advertisers.
Go premium forTo post a comment, you need to register for a LEEDuser Basic membership (free) or login to your existing profile.
Trista Brown
Project DirectorWSP USA
449 thumbs up
July 27, 2020 - 6:46 pm
Hi Xin, onsite reuse is an acceptable strategy for this credit. You don't need to have other measures in place if you can meet the threshold with reuse. But - if water reuse but its not enough to meet the threshold, you'll have to implement additional measures.