Hi. We have a Campus school project with 4 buildings to be certified under v4, two of which are to be BD+C for Schools and the other BD+C NC. The LT Credit Bicycle Facilities is a Campus credit, however the campus guidance we can find is only for v3 and states that showers and bicycle storage must be within 200 yards of each of the building entrances. Is this still current in v4?
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for $... »
Tristan Roberts
RepresentativeVermont House of Representatives
LEEDuser Expert
11478 thumbs up
August 26, 2017 - 12:32 pm
I would assume so. I have reposted this under our campus guidance page, where I'm hoping USGBC will weigh in.
Kimberly Schlaepfer
Sustainability Coordinator LEED AP O+M, BD+C75 thumbs up
September 1, 2017 - 3:01 pm
Hi Phillipa,
The v2009 requirement is that the bicycle facilities must be within 200 yards of the building entrances, regardless of if it was a campus or not. In v4 this was updated to be 100 ft from any main entrance for short-term storage and 100 ft from any functional entrance for long-term storage. I believe, if you are pursuing this credit for the campus under the v4 rating system you should use the v4 requirements to demonstrate compliance.
I hope this helps!