Hello!
We are pursuing LEED NC 2009. Our project is a Data center office building which will be operated 24 hours, 365 days per year, with No transients, visitors or residents in the building. The shift work is distributed as following:
From Monday to Friday:
8:00am - 3:00pm 25 persons
9:30am - 7:00pm 19 persons
11:00am - 6:00pm 7 persons
3:00pm - 10:00pm 23 persons
10:00pm - 8:00am 14 persons

Saturdays - Sundays and Holidays:
10:00am - 10:00pm 15 persons
10:00pm - 10:00am 15 persons

How do we determine FTE and daily occupancy this in this case? Can someone help me in this calculation?
Thanks a lot!