FAQs about EAp2 :

Our project has a large process load—75%. Despite our efforts to make an efficient HVAC design, the cost savings are minimal. What can we do to earn this prerequisite and be eligible for LEED certification? Is there any flexibility in how we model the p

Can SHGC be higher in the proposed than in the baseline model?

Our process load is higher than 25%. Do we have to justify that?

Do I need to justify the electrical and fuel rates I am using in my model?

Our local code references ASHRAE 90.1-2010. Should I use that for my documentation, or 90.1-2007?

Can I claim exterior lighting savings for canopy lighting even though a baseline model cannot include shading elements?

The project is built on a site with existing exterior lighting installed. How should this be accounted for?

Can mezzanines open to floors below be excluded from the energy model?

How do I provide a zip code for an international location?

For a project outside the U.S., how do I determine the climate zone?

For a project outside the U.S., how do I determine the Target Finder score?

Do hotel rooms need automatic light shut-off control?

How commonly are the 90.1 mandatory compliance forms submitted as part of EAp2/EAc1?

The Section 9 space-by-space method does not include residential space types. What should I use?

Can the Passive House Planning Package (PHPP) be used to energy model for LEED?

Is it acceptable to model a split-type AC with inverter technology compressor as a heat pump, like modeling VRF?

Can the Trace 700 'LEED Energy Performance Summary Report' by uploaded to LEED Online in lieu of the Section 1.4 tables spreadsheet?

A portion of our building envelope is historic. Can we exclude it from our model?

Which baseline HVAC system do I use if my building has no heating or air conditioning?

For an existing building, do I need to rotate the model?

View answers »

Forum discussion

NC-2009 EAp2:Minimum Energy Performance

BASELINE - Fan Power adjustment

Greetings, In the design project we are modeling, there are systems which In the Baseline model are to be classified to System 9, System 11 (90.1-3013 for Data Centers) and Parking garage ventilation. In the design project all these ventilation and AHU equipment serving these systems are structured with sound attenuators, filters and all of them are with fully ducted return/exhaust system. Following the G3.1.2.10, there isn't the component "A" in their formula (System 9 and 11). Does it mean that for these systems there will be no Fan Power Adjustment allowed regardless of what is in the project design. The parking garage ventilation is not mentioned there, but its fan power estimation is as this of System 9, meaning also no Adjustment. Your assistance is highly appreciated. Thanks.

0

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Tue, 09/05/2017 - 15:13

Correct there are no fan power adjustments for a system 9. Not sure about a system 11 but sounds like you are not seeing it so probably no adjustments for that either.

Add new comment