This project is a CI fit out for 100% of the leasable floor area of the base building, which is currently being certified as Core and shell. The scope for CI does not include anything related to envelope and for HVAC only indoor units. 

1. What is the HVAC system and envelope for the baseline model?  Is it according to Table G3.1.1A or identical to the proposed?

2. If it according to Table G3.1.1A, Can we use/update the same baseline energy model developed for the CS certification?

Many thanks.