ASHRAE puts a requirement to keep in electrical services on the feeders max 2% voltage drop and on the branch circuits max 3%.
Is it possible to keep this 5% but split in any other way for example feeders 3% and branch circuits 2%?
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
Marcus Sheffer
LEED Fellow7group / Energy Opportunities
LEEDuser Expert
5909 thumbs up
April 2, 2014 - 10:15 am
This LEED Interpretation addresses this issue ID#10218 - 07/01/2012