Our CS building is scheduled for commissioning end of August. Can tenants start outfitting their spaces before this date which will enable their employees to work from September. If this is possible, are their any limitation with respect to tenants occupancy before the building is complete.
Many Thanks
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
Dave Hubka
Practice Leader - SustainabilityEUA
LEEDuser Expert
530 thumbs up
February 5, 2015 - 3:17 pm
While not preferred, tenants can start outfitting their space before the commissioning occurs. If the tenant buildouts are under seperate contracts there are no limitation with respect to tenant occupancy before the building is complete. If the tenant buildouts are under the same contract as the Core & Shell work, and the tenant buildout work exceeds 50% of the total building floor area, then LEED for New Construction would need to be pursued.
hope this helps.