We have a site that is partially a greenfield and partially previously developed (remediated brownfield). In this instance can we apply the parameters of case 1 to the greenfield portion and the parameters of case 2 to the remediated brownfield portion? Thanks in advance for the help!

3

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Fri, 03/25/2011 - 21:44

Shannon, this sounds like the most appropriate approach for your project. You may want to submit a CIR or LEED Interpretation for confirmation from GBCI but if you are meeting all the case 1 requirements and limiting disturbance for the greenfield areas, and then also meeting case 2 requirements and protecting / restoring vegetation with the required %, I would see this as a reasonable compliance path to meet the credit. Let us know how it goes.

Add new comment

To post a comment, you need to register for a LEEDuser Basic membership (free) or login to your existing profile.