We are going to apply for 1 point in credit IEQc3.1 but the Contractor is trying to avoid any ventilation during construction:
- no natural ventilation
- no ventilation by permanent system
- no any temporary/portable ventilation units.
I have not found any information that air cleaning/ventilation MUST take place and how often.
ALL absorptive materials will be protected, for construction works low-VOC materials will be used.
Could you please advice if its enough to make house keeping by sweeping (including by vacuum-cleaners), wet mopping and using low-VOC cleaners without any air cleaning?