If we are designing a project on a 100% greenfield land, therefore no previously developed area is present. How can we achieve credit for option 1, or do we necessarily go with option 2 in order to gain credit requirements?
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for $12.95 »
Marc Mondor
PrincipalEvolve LLC
59 thumbs up
September 2, 2020 - 7:01 pm
Yes, the reference manual states that Option 2 must be used if site is 100% greenfield.