If we are designing a project on a 100% greenfield land, therefore no previously developed area is present. How can we achieve credit for option 1, or do we necessarily go with option 2 in order to gain credit requirements?
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
Marc Mondor
PrincipalEvolve LLC
59 thumbs up
September 2, 2020 - 7:01 pm
Yes, the reference manual states that Option 2 must be used if site is 100% greenfield.