ND-v2009 SLLp5: Floodplain avoidance Required

LEEDuser’s viewpoint

Explore this LEED credit

Post your questions on this credit in the forum, and click on the credit language tab to review to the LEED requirements.

Credit language

USGBC logo

© Copyright U.S. Green Building Council, Inc. All rights reserved.

Requirements

To protect life and property, promote open space and habitat conservation, and enhance water quality and natural hydrological systems.

Option 1. Sites without floodplains
Locate on a site that does not contain any land within a 100-year high- or moderate-risk floodplain as defined and mapped by the Federal Emergency Management Agency (FEMA) (or a local equivalent for projects outside the U.S.) or a state or local floodplain management agency, whichever is more recent. For projects in places without legally adopted flood hazard maps or legal designations, locate on a site that is entirely outside any floodplain subject to a 1% or greater chance of flooding in any given year.

OR

Option 2. Infill or previously developed sites with floodplains
Locate the project on an infill site or a previously developed site or in a nonconveyance area of river or coastal floodplain without storm surge potential where compensatory storage is used in accordance with a FEMA-approved mitigation plan (or a local equivalent for projects outside of the U.S.). Comply with the National Flood Insurance Program (NFIP) requirements (or a local equivalent for projects outside of the U.S.) for developing any portions of the site that lie within a 100-year high-or moderate-risk floodplain, as defined in Option 1. If the project includes construction of any critical facility, such as a hospital, water and sewage treatment facility, emergency center, or fire or police station, the critical facility must be designed and built so as to be protected and operable during a 500-year event. OR For any portion of the site within the flood hazard area, design buildings in accordance with American Society of Civil Engineers Standard 24-05 (ASCE 24). If the project includes construction of a critical facility that is intended to remain operational in the event of a flood, or whose function is critical for post flood recovery, design the facility to be protected and operable at the floodwater levels specified in ASCE 24, or at the water levels represented by a 0.2% annual chance (500-year) flood, whichever is higher. For the purpose of this requirement, critical facilities include, but are not limited to, hospitals, emergency operations centers, building or portions of buildings designated as emergency shelters, water and sewage treatment facilities, and fire and police stations.

OR

Option 3. All other sites with floodplains
If any part of the site is located within a 100-year high- or moderate-risk floodplain, as defined above, develop only on portions of the site that are not in the floodplain, or that have been previously developed, or that are in a nonconveyance area of river or coastal floodplain without storm surge potential where compensatory storage is used in accordance with a FEMA-approved mitigation plan (or a local equivalent for projects outside of the U.S.). Previously developed portions in the floodplain must be developed according to NFIP requirements (or a local equivalent for projects outside of the U.S.). If development includes construction of any critical facility, as described above, the critical facility must be designed and built so as to be protected and operable during a 500-year event. OR For any portion of the site within the flood hazard area, design buildings in accordance with American Society of Civil Engineers Standard 24-05 (ASCE 24) or local floodplain management entity. If the project includes construction of a critical facility that is intended to remain operational in the event of a flood, or whose function is critical for post flood recovery, design the facility to be protected and operable at the floodwater levels specified in ASCE 24, or at the water levels represented by a 0.2% annual chance (500-year) flood, whichever is higher. For the purpose of this requirement, critical facilities include, but are not limited to, hospitals, emergency operations centers, building or portions of buildings designated as emergency shelters, water and sewage treatment facilities, and fire and police stations. See all forum discussions about this credit »

What does it cost?

Cost estimates for this credit

On each BD+C v4 credit, LEEDuser offers the wisdom of a team of architects, engineers, cost estimators, and LEED experts with hundreds of LEED projects between then. They analyzed the sustainable design strategies associated with each LEED credit, but also to assign actual costs to those strategies.

Our tab contains overall cost guidance, notes on what “soft costs” to expect, and a strategy-by-strategy breakdown of what to consider and what it might cost, in percentage premiums, actual costs, or both.

This information is also available in a full PDF download in The Cost of LEED v4 report.

Learn more about The Cost of LEED v4 »

This article is BuildingGreen Premium content

Two ways to read the full article and get CEUs:

Sign up for BuildingGreen Premium to access all our premium content

Join for just $.../month »

Purchase this article to get online access and a printable PDF.

Buy it now for $... »

Already a premium member? Log in now

To read the full article, subscribe now to BuildingGreen Premium

For full access, sign up now for LEEDuser Premium

LEEDuser tip sheets, written by our team of LEED experts, fill gaps in knowledge we’ve observed between the LEED Reference Guide, LEED Online, and LEED Interpretations. We update them regularly so that our members get the most relevant guidance for current issues on their projects.

( does not provide premium access to LEEDuser)

Go premium for just $... » Go premium for just $... » Firm or campus members – click here »

Your 15-day free trial expired on

Already a premium member? Log in now

Addenda

7/1/2014Updated: 2/14/2015
Global ACP
Description of change:
Delete "as defined by FEMA" from the last sentence.
Add a section:
"OR
For any portion of the site within the flood hazard area, design buildings in accordance with American Society of Civil Engineers Standard 24-05 (ASCE 24). If the project includes construction of a critical facility that is intended to remain operational in the event of a flood, or whose function is critical for post flood recovery, design the facility to be protected and operable at the floodwater levels specified in ASCE 24, or at the water levels represented by a 0.2% annual chance (500-year) flood, whichever is higher. For the purpose of this requirement, critical facilities include, but are not limited to, hospitals, emergency operations centers, building or portions of buildings designated as emergency shelters, water and sewage treatment facilities, and fire and police stations."

Campus Applicable
No
Internationally Applicable:
Yes
7/1/2014Updated: 2/14/2015
Global ACP
Description of change:
Delete "as defined by FEMA" from the last sentence.
Add a section:
"OR
For any portion of the site within the flood hazard area, design buildings in accordance with American Society of Civil Engineers Standard 24-05 (ASCE 24) or local floodplain management entity. If the project includes construction of a critical facility that is intended to remain operational in the event of a flood, or whose function is critical for post flood recovery, design the facility to be protected and operable at the floodwater levels specified in ASCE 24, or at the water levels represented by a 0.2% annual chance (500-year) flood, whichever is higher. For the purpose of this requirement, critical facilities include, but are not limited to, hospitals, emergency operations centers, building or portions of buildings designated as emergency shelters, water and sewage treatment facilities, and fire and police stations."

Campus Applicable
No
Internationally Applicable:
Yes
7/1/2014Updated: 2/14/2015
Global ACP
Description of change:
Add a sentence: "For projects in places without legally adopted flood hazard maps or legal designations, locate on a site that is entirely outside any floodplain subject to a 1% or greater chance of flooding in any given year."
Add "(or a local equivalent for projects outside the U.S.)" behind "Federal Emergency Management Agency (FEMA)."
Campus Applicable
No
Internationally Applicable:
Yes
See all forum discussions about this credit »

Documentation toolkit

The motherlode of cheat sheets

LEEDuser’s Documentation Toolkit is loaded with calculators to help assess credit compliance, tracking spreadsheets for materials, sample templates to help guide your narratives and LEED Online submissions, and examples of actual submissions from certified LEED projects for you to check your work against. To get your plaque, start with the right toolkit.

This article is BuildingGreen Premium content

Two ways to read the full article and get CEUs:

Sign up for BuildingGreen Premium to access all our premium content

Join for just $.../month »

Purchase this article to get online access and a printable PDF.

Buy it now for $... »

Already a premium member? Log in now

To read the full article, subscribe now to BuildingGreen Premium

For full access, sign up now for LEEDuser Premium

LEEDuser tip sheets, written by our team of LEED experts, fill gaps in knowledge we’ve observed between the LEED Reference Guide, LEED Online, and LEED Interpretations. We update them regularly so that our members get the most relevant guidance for current issues on their projects.

( does not provide premium access to LEEDuser)

Go premium for just $... » Go premium for just $... » Firm or campus members – click here »

Your 15-day free trial expired on

Already a premium member? Log in now

USGBC logo

© Copyright U.S. Green Building Council, Inc. All rights reserved.

Requirements

To protect life and property, promote open space and habitat conservation, and enhance water quality and natural hydrological systems.

Option 1. Sites without floodplains
Locate on a site that does not contain any land within a 100-year high- or moderate-risk floodplain as defined and mapped by the Federal Emergency Management Agency (FEMA) (or a local equivalent for projects outside the U.S.) or a state or local floodplain management agency, whichever is more recent. For projects in places without legally adopted flood hazard maps or legal designations, locate on a site that is entirely outside any floodplain subject to a 1% or greater chance of flooding in any given year.

OR

Option 2. Infill or previously developed sites with floodplains
Locate the project on an infill site or a previously developed site or in a nonconveyance area of river or coastal floodplain without storm surge potential where compensatory storage is used in accordance with a FEMA-approved mitigation plan (or a local equivalent for projects outside of the U.S.). Comply with the National Flood Insurance Program (NFIP) requirements (or a local equivalent for projects outside of the U.S.) for developing any portions of the site that lie within a 100-year high-or moderate-risk floodplain, as defined in Option 1. If the project includes construction of any critical facility, such as a hospital, water and sewage treatment facility, emergency center, or fire or police station, the critical facility must be designed and built so as to be protected and operable during a 500-year event. OR For any portion of the site within the flood hazard area, design buildings in accordance with American Society of Civil Engineers Standard 24-05 (ASCE 24). If the project includes construction of a critical facility that is intended to remain operational in the event of a flood, or whose function is critical for post flood recovery, design the facility to be protected and operable at the floodwater levels specified in ASCE 24, or at the water levels represented by a 0.2% annual chance (500-year) flood, whichever is higher. For the purpose of this requirement, critical facilities include, but are not limited to, hospitals, emergency operations centers, building or portions of buildings designated as emergency shelters, water and sewage treatment facilities, and fire and police stations.

OR

Option 3. All other sites with floodplains
If any part of the site is located within a 100-year high- or moderate-risk floodplain, as defined above, develop only on portions of the site that are not in the floodplain, or that have been previously developed, or that are in a nonconveyance area of river or coastal floodplain without storm surge potential where compensatory storage is used in accordance with a FEMA-approved mitigation plan (or a local equivalent for projects outside of the U.S.). Previously developed portions in the floodplain must be developed according to NFIP requirements (or a local equivalent for projects outside of the U.S.). If development includes construction of any critical facility, as described above, the critical facility must be designed and built so as to be protected and operable during a 500-year event. OR For any portion of the site within the flood hazard area, design buildings in accordance with American Society of Civil Engineers Standard 24-05 (ASCE 24) or local floodplain management entity. If the project includes construction of a critical facility that is intended to remain operational in the event of a flood, or whose function is critical for post flood recovery, design the facility to be protected and operable at the floodwater levels specified in ASCE 24, or at the water levels represented by a 0.2% annual chance (500-year) flood, whichever is higher. For the purpose of this requirement, critical facilities include, but are not limited to, hospitals, emergency operations centers, building or portions of buildings designated as emergency shelters, water and sewage treatment facilities, and fire and police stations.