Forum
Forum » EBOM-v4 EAc2
Topic | Recent |
---|---|
LEED v4 EBOM- CommissioningEBOM-v4 EAc2: Existing Building Commissioning—Implementationposted by Aber Alvi on Mar 22, 2018, 1:04 am
A project for which level 2 energy audit had been carried out and implemented more than a year ago, can that energy audit report and the measurement and verification results from the last one... Last reply: Trista Brown, May 24, 2018, 8:26 pm |
|
V4 EBOM- CommissioningEBOM-v4 EAc2: Existing Building Commissioning—Implementationposted by Meier Corporate Account on Jun 16, 2016, 3:42 pm
Good Afternoon, Our manufacturing plant was constructed in 2014-2015 and went online in August of 2015. We were originally going to open LEED certified, but due to a tight schedule this... Last reply: Dave Hubka, Jun 20, 2016, 5:47 pm |