Further Explanation: Insert the following content as the third section in Further Explanation, between current sections "Prescriptive Path" and "Creating a Compliant 90.1 Energy Model":
"Fundamental Commissioning of Central HVAC and Service Water Heating Systems
Engage a
commissioning authority (
CxA) with the following qualifications:
• The
CxA must have documented
commissioning process experience on at least two building projects with a similar scope of work.
• The
CxA may be a qualified employee of the owner, an independent consultant, or an employee of the design or construction firm who is not part of the project’s design or construction team, or a disinterested subcontractor of the design or construction team
• For project types meeting all of the following criteria, the
CxA may be a qualified member of the design or construction team, but the designated
CxA must report all findings directly to the owner.
o Projects where the central systems serving residential spaces are limited to service water heating, fresh air systems, central exhaust air systems, and/or pumps and heat exchangers used in conjunction with District Energy Systems (where the heating and cooling are generated upstream of the building)
o Projects where the total commercial gross area does not exceed 20,000 square feet (commercial area refers to office, retail, hospitality, or similar occupancy, but does not refer to common residential areas such as corridors, lobbies, fitness areas, etc. used to support the residential functions of the building)
Meet the performance testing and ongoing maintenance requirements of EA Prerequisite Fundamental Commissioning and Verification of LEED v4 for New Construction for central commercial heating, cooling, water heating and ventilation systems. The requirements include the following:
• Develop a system test procedure.
• Verify system test execution.
• Maintain an issues and benefits log throughout the
commissioning process.
• Document all findings and recommendations and report directly to the owner throughout the process.
• Prepare or oversee preparation of a
current facilities requirements and
operations and maintenance plan documenting information necessary for efficient building operations.
Systems that must be included in the
commissioning scope of work include:
• Central HVAC systems serving residential spaces including but not limited to:
o Chillers
o Boilers
o Pumps
o Cooling towers
o Heat exchangers
o Ground source loops
o Variable refrigerant flow shared outdoor units, and the associated refrigerant lines
o Air handling units
o Fresh air systems
o Central exhaust systems
o Building automation system HVAC controls
• Central service water heating systems serving residential spaces
• Garage exhaust and/or heating systems
• Snow melt systems
• HVAC and service water heating systems and pool heating serving common areas and commercial areas
o Exception,
commissioning of common and commercial areas is not required if the combined capacity of HVAC and service water equipment serving common areas and commercial areas is less than 20 tons cooling, 500,000 btuh heating, or 10,000 cfm
The
CxA should be engaged as early as possible in the design phase, and must be engaged no later than the completion of contract documents. Functional testing for all systems in the
commissioning scope of work must commence before the completion of the construction phase."
Further Explanation: Insert the following content as the fourth section in Further Explanation, after the new section "Fundamental Commissioning of Central HVAC and Service Water Heating Systems" and before the section "Creating a Compliant 90.1 Energy Model":
"Functional Performance Tests
The functional performance test reports typically have the following sections:
• Date and time of test
• Individuals present during testing
• Visual inspection observations. Before testing, the
CxA should perform a visual inspection and document any issues or relevant observations.
• Sensor checks. The sensors are checked individually to make sure they are reading properly and are in the correct locations, per the design documents.
• Device checks. Each device is checked to verify that it can open, close, modulate, start, stop, energize in stages, etc.
• Operating mode tests. A system is run through each type of operating mode including but not limited to start up, shutdown, capacity modulation, emergency and failure modes, alarm scenarios, occupied mode and unoccupied mode, and interlocks with other equipment.
• Results. Indicate whether the system passed, failed, or requires retesting."
Technical Resources: Add the following resource at the end of this section:
"Functional Test Guide:
http://www.ftguide.org/ftct/testdir.htm"
Definitions: Add the following term and definition as the first term in this section:
"Central HVAC System: HVAC or water heating systems, or components of those systems that serve multiple residential units, common areas, or commercial spaces."
Verification and Submittals: In the section "Supporting verification materials, made available by the project team" add the following additional items in a bulleted list beneath the Multifamily Midrise bullet "Provide energy model for USGBC review.":
• Name of Commissioning Provider
• Commissioning Report with date of completion
• List of Systems Commissioned
• Full issues summary log
• Number of equipment functional tests performed
• At least 2 sample function tests (for two different system types)
• Date of Acceptance by Owner
• Expected completion date of Commissioning Report (usually one year after Owner’s acceptance)