LEED CREDIT

ND-v2009 GIBp4: Construction Activity Pollution Prevention Required

LEEDuser’s viewpoint

Explore this LEED credit

Post your questions on this credit in the forum, and click on the credit language tab to review to the LEED requirements.

Credit language

USGBC logo

© Copyright U.S. Green Building Council, Inc. All rights reserved.

Requirements

Create and implement an erosion and sedimentation control plan for all new construction activities associated with the project. The plan must incorporate practices such as phasing, seeding, grading, mulching, filter socks, stabilized site entrances, preservation of existing vegetation, and other best management practices (BMPs) to control erosion and sedimentation in runoff from the entire project site during construction. The plan must list the BMPs employed and describe how they accomplish the following objectives:

  1. Prevent loss of soil during construction by stormwater runoff and/or wind erosion, including but not limited to stockpiling of topsoil for reuse.
  2. Prevent sedimentation of any affected stormwater conveyance systems or receiving streams.
  3. Prevent polluting the air with dust and particulate matter.
The erosion and sedimentation control plan must describe how the project team will do the following:
  1. Preserve vegetation and mark clearing limits.
  2. Establish and delineate construction access.
  3. Control flow rates.
  4. Install sediment controls.
  5. Stabilize soils.
  6. Protect slopes.
  7. Protect drain inlets.
  8. Stabilize channels and outlets.
  9. Control pollutants.
  10. Control dewatering.
  11. Maintain the BMPs.
  12. Manage the erosion and sedimentation control plan.
Select BMPs that are consistent with Green Infrastructure and Low Impact Development (LID) strategies such as the Washington State Department of Ecology’s Stormwater Management Manual for Western Washington, Volume II, Construction Stormwater Pollution Prevention (2005 edition), or a local equivalent. Choose BMPs that are the most stringent and appropriate to the project site and region. BMPs must comply with all national, state, and local erosion and sedimentation control regulations. See all forum discussions about this credit »

What does it cost?

Cost estimates for this credit

On each BD+C v4 credit, LEEDuser offers the wisdom of a team of architects, engineers, cost estimators, and LEED experts with hundreds of LEED projects between then. They analyzed the sustainable design strategies associated with each LEED credit, but also to assign actual costs to those strategies.

Our tab contains overall cost guidance, notes on what “soft costs” to expect, and a strategy-by-strategy breakdown of what to consider and what it might cost, in percentage premiums, actual costs, or both.

This information is also available in a full PDF download in The Cost of LEED v4 report.

Learn more about The Cost of LEED v4 »

This article is BuildingGreen Premium content

Two ways to read the full article and get CEUs:

Sign up for BuildingGreen Premium to access all our premium content

Join for just $.../month »

Purchase this article to get online access and a printable PDF.

Buy it now for $... »

Already a premium member? Log in now

To read the full article, subscribe now to BuildingGreen Premium

For full access, sign up now for LEEDuser Premium

LEEDuser tip sheets, written by our team of LEED experts, fill gaps in knowledge we’ve observed between the LEED Reference Guide, LEED Online, and LEED Interpretations. We update them regularly so that our members get the most relevant guidance for current issues on their projects.

( does not provide premium access to LEEDuser)

Go premium for just $... » Go premium for just $... » Firm or campus members – click here »

Your 15-day free trial expired on

Already a premium member? Log in now

Addenda

7/1/2014Updated: 2/14/2015
Global ACP
Description of change:
Replace last paragraph with the following: “Select BMPs that are consistent with Green Infrastructure and Low Impact Development (LID)strategies such as the Washington State Department of Ecology’s Stormwater Management Manual for Western Washington, Volume II, Construction Stormwater Pollution Prevention (2005 edition), or a local equivalent. Choose BMPs that are the most stringent and appropriate to the project site and region. BMPs must comply with all national, state, and local erosion and sedimentation control regulations.”
Campus Applicable
No
Internationally Applicable:
Yes
See all forum discussions about this credit »

Documentation toolkit

The motherlode of cheat sheets

LEEDuser’s Documentation Toolkit is loaded with calculators to help assess credit compliance, tracking spreadsheets for materials, sample templates to help guide your narratives and LEED Online submissions, and examples of actual submissions from certified LEED projects for you to check your work against. To get your plaque, start with the right toolkit.

This article is BuildingGreen Premium content

Two ways to read the full article and get CEUs:

Sign up for BuildingGreen Premium to access all our premium content

Join for just $.../month »

Purchase this article to get online access and a printable PDF.

Buy it now for $... »

Already a premium member? Log in now

To read the full article, subscribe now to BuildingGreen Premium

For full access, sign up now for LEEDuser Premium

LEEDuser tip sheets, written by our team of LEED experts, fill gaps in knowledge we’ve observed between the LEED Reference Guide, LEED Online, and LEED Interpretations. We update them regularly so that our members get the most relevant guidance for current issues on their projects.

( does not provide premium access to LEEDuser)

Go premium for just $... » Go premium for just $... » Firm or campus members – click here »

Your 15-day free trial expired on

Already a premium member? Log in now

USGBC logo

© Copyright U.S. Green Building Council, Inc. All rights reserved.

Requirements

Create and implement an erosion and sedimentation control plan for all new construction activities associated with the project. The plan must incorporate practices such as phasing, seeding, grading, mulching, filter socks, stabilized site entrances, preservation of existing vegetation, and other best management practices (BMPs) to control erosion and sedimentation in runoff from the entire project site during construction. The plan must list the BMPs employed and describe how they accomplish the following objectives:

  1. Prevent loss of soil during construction by stormwater runoff and/or wind erosion, including but not limited to stockpiling of topsoil for reuse.
  2. Prevent sedimentation of any affected stormwater conveyance systems or receiving streams.
  3. Prevent polluting the air with dust and particulate matter.
The erosion and sedimentation control plan must describe how the project team will do the following:
  1. Preserve vegetation and mark clearing limits.
  2. Establish and delineate construction access.
  3. Control flow rates.
  4. Install sediment controls.
  5. Stabilize soils.
  6. Protect slopes.
  7. Protect drain inlets.
  8. Stabilize channels and outlets.
  9. Control pollutants.
  10. Control dewatering.
  11. Maintain the BMPs.
  12. Manage the erosion and sedimentation control plan.
Select BMPs that are consistent with Green Infrastructure and Low Impact Development (LID) strategies such as the Washington State Department of Ecology’s Stormwater Management Manual for Western Washington, Volume II, Construction Stormwater Pollution Prevention (2005 edition), or a local equivalent. Choose BMPs that are the most stringent and appropriate to the project site and region. BMPs must comply with all national, state, and local erosion and sedimentation control regulations.
See all LEEDuser forum discussions about this credit » Unsubscribe from discussions about ND-v2009 GIBp4