LEED CREDIT

ND-v2009 NPDp2: Compact development Required

LEEDuser’s viewpoint

Explore this LEED credit

Post your questions on this credit in the forum, and click on the credit language tab to review to the LEED requirements.

Credit language

USGBC logo

© Copyright U.S. Green Building Council, Inc. All rights reserved.

Requirements

Projects in transit corridors
For projects with existing and/or planned transit service (i.e., service with the funding commitments specified in SLL Prerequisite 1, Smart Location) that meets or exceeds the 2-point threshold in SLL Credit 3, Locations with Reduced Automobile Dependence, Option 1, build at the following densities, based on the walk distances to the transit service specified in SLL Credit 3:
  1. For residential components located within the walk distances: 12 or more dwelling units per acre (30 DU/hectare) of buildable land available for residential uses.
  2. For residential components falling outside the walk distances: 7 or more dwelling units per acre (17.5 DU/hectare) of buildable land available for residential uses.
  3. For nonresidential components located within the walk distances: 0.80 floor-area ratio (FAR) or greater of buildable land available for nonresidential uses.
  4. For nonresidential components falling outside the walk distances: 0.50 FAR or greater of buildable land available for nonresidential uses.
    1. If the project location is served by a transit agency that has specified guidelines for minimum service densities that are greater than the densities required by this prerequisite, the project must achieve those service densities instead.

      OR

      Option 2. All other projects
      Build any residential components of the project at a density of 7 dwelling units per acre (17.5 DU/hectare) of buildable land available for residential uses. AND Build any nonresidential components of the project at a density of 0.50 FAR or greater of buildable land available for nonresidential uses.
      For all projects
      Density calculations include all planned and existing buildings within the project boundary, excluding those portions of parking structures devoted exclusively to parking. The specified density must be achieved within five years of the date that the first building of any type is occupied. If one component of the project, residential or nonresidential, meets the minimum density requirement but the other component does not, include only the qualifying density. Use that component’s dwelling units or nonresidential floor area in the numerator and the total buildable land area in the denominator. If the resulting density meets the minimum requirement, the prerequisite is achieved.
See all forum discussions about this credit »

What does it cost?

Cost estimates for this credit

On each BD+C v4 credit, LEEDuser offers the wisdom of a team of architects, engineers, cost estimators, and LEED experts with hundreds of LEED projects between then. They analyzed the sustainable design strategies associated with each LEED credit, but also to assign actual costs to those strategies.

Our tab contains overall cost guidance, notes on what “soft costs” to expect, and a strategy-by-strategy breakdown of what to consider and what it might cost, in percentage premiums, actual costs, or both.

This information is also available in a full PDF download in The Cost of LEED v4 report.

Learn more about The Cost of LEED v4 »

Addenda

7/1/2014Updated: 2/14/2015
Global ACP
Description of change:
Table 1.
Add second column, Residential density (DU/hectare), with the following values"
> 25 and ≤ 32
> 32 and ≤ 45
> 45 and ≤ 62
> 62 and ≤ 94
> 94 and ≤ 156
> 156

Replace all instances of "the total square footage" with "the total floor area."
Add "(hectare)" after "acre"
Campus Applicable
No
Internationally Applicable:
Yes
See all forum discussions about this credit »

Documentation toolkit

The motherlode of cheat sheets

LEEDuser’s Documentation Toolkit is loaded with calculators to help assess credit compliance, tracking spreadsheets for materials, sample templates to help guide your narratives and LEED Online submissions, and examples of actual submissions from certified LEED projects for you to check your work against. To get your plaque, start with the right toolkit.

USGBC logo

© Copyright U.S. Green Building Council, Inc. All rights reserved.

Requirements

Projects in transit corridors
For projects with existing and/or planned transit service (i.e., service with the funding commitments specified in SLL Prerequisite 1, Smart Location) that meets or exceeds the 2-point threshold in SLL Credit 3, Locations with Reduced Automobile Dependence, Option 1, build at the following densities, based on the walk distances to the transit service specified in SLL Credit 3:
  1. For residential components located within the walk distances: 12 or more dwelling units per acre (30 DU/hectare) of buildable land available for residential uses.
  2. For residential components falling outside the walk distances: 7 or more dwelling units per acre (17.5 DU/hectare) of buildable land available for residential uses.
  3. For nonresidential components located within the walk distances: 0.80 floor-area ratio (FAR) or greater of buildable land available for nonresidential uses.
  4. For nonresidential components falling outside the walk distances: 0.50 FAR or greater of buildable land available for nonresidential uses.
    1. If the project location is served by a transit agency that has specified guidelines for minimum service densities that are greater than the densities required by this prerequisite, the project must achieve those service densities instead.

      OR

      Option 2. All other projects
      Build any residential components of the project at a density of 7 dwelling units per acre (17.5 DU/hectare) of buildable land available for residential uses. AND Build any nonresidential components of the project at a density of 0.50 FAR or greater of buildable land available for nonresidential uses.
      For all projects
      Density calculations include all planned and existing buildings within the project boundary, excluding those portions of parking structures devoted exclusively to parking. The specified density must be achieved within five years of the date that the first building of any type is occupied. If one component of the project, residential or nonresidential, meets the minimum density requirement but the other component does not, include only the qualifying density. Use that component’s dwelling units or nonresidential floor area in the numerator and the total buildable land area in the denominator. If the resulting density meets the minimum requirement, the prerequisite is achieved.
See all LEEDuser forum discussions about this credit » Unsubscribe from discussions about ND-v2009 NPDp2