In alphabetical order, add the term "Gross floor area (based on ASHRAE definition) is the sum
In alphabetical order, add the term "Gross floor area (based on ASHRAE definition) is the sum
Replace the definition of "chlorofluorocarbons (CFCs)" with "a compound of carbon, hydrogen, chlorine and fluorine, once commonly used in refrigeration, that depletes the stratospheric ozone layer."
Replace the definition of "chlorofluorocarbons (CFCs)" with "a compound of carbon, hydrogen, chlorine and fluorine, once commonly used in refrigeration, that depletes the stratospheric ozone layer."
In alphabetical order, add the following definition for occupied spaces, "Occupied Spaces are defined as enclosed spaces that can accommodate human activities. Occupied spaces are further classified as regularly occupied or non-regularly occupied spaces based on the duration of the occupancy, individual or multi-occupant based on the quantity of occupants, and densely or non-densely occupied spaces based upon the concentration of occupants in the space."
Edit the guidance to read:
"Group Approach
All buildings in the group project may be documented as one as long as all buildings in the group are served by the same cooling tower(s). If different buildings in the group are served by different cooling towers, submit this credit separately for each building in the group.
Campus Approach
Eligible. All buildings must use the same cooling tower."
After the first paragraph, add the following:/n
"For an expanded reference of international locations, ASHRAE 169-2013 Table A-5 (Canada) or Table A-6 (International) may be consulted. ASHRAE 169-2013 subdivides Climate Zone 1 into two climate zones (Climate Zone 1 and Climate Zone 0). Locations listed in ASHRAE 169-2013 in Climate Zone 1 and Climate Zone 0 should be considered Climate Zone 1 under ASHRAE 90.1-2010."
Replace the second paragraph with the following:
All DES Systems: The team may enter the output from the DES delivered to the project building into the Portfolio Manager tool as site energy from a district system (e.g., district chilled water); Portfolio Manager then converts it to source energy based on ENERGY STAR’s standard methodology.
Replace the third paragraph with the following:
Under bullet for "Products" add new guidance to the last sub-bullet so it reads as follows:
Edit the guidance to read:
"Group Approach
All buildings in the group may be documented as one.
Campus Approach
Option 1: Eligible.
Option 2: Ineligible. Each LEED project may pursue the credit individually.
Option 3: Ineligible. Each LEED project may pursue the credit individually.
Option 4: Ineligible. Each LEED project may pursue the credit individually."
In the sixth row ("Lavatory Faucet") row of the table in the 11/2/2009 addenda, replace the duration (sec) of 15 with 30; replace the related note below table with "Default duration for the metering type / autocontrol faucet is 15 seconds for the baseline and 12 seconds for the design case."