We’re can’t earn this credit now but we’d like to when we go for EBOM recertification. How can reduce the heat island affect of our building’s site hardscape over time?

Here’s some options to consider for reducing heat island affect:

Add vegetated islands to surface parking that provide both heat island reduction and stormwater infiltration benefitsInstall open-grid paving in areas like walkways, patios, plazas, and courtyards as existing hardscape ages and needs to be replacedWhen your surface parking lot needs to be repaved, consider installing a high-albedo permeable or porous paver system designed specifically for parking applications.

Our building doesn’t have any onsite parking. Can we earn this credit by documenting that we don’t provide parking to occupants?

Yes, this is an acceptable path to credit compliance per LEED Interpretation #5370, as long as no nearby offsite parking facilities are leased or owned by the building owner, property manager, or tenants for use by building occupants. See the Interpretation for additional information on demonstrating compliance through this path.

Our multi-story, multi-tenant building has many different floor plans and cubical configurations. Do we need to provide section drawings and floor plans for every space in order to document Option 2: Views?

To adequately show that at least 45% of regularly occupied spaces comply with vision requirements, you’ll have to provide documentation showing line of sight for the spaces that are contributing to credit achievement, even if floor plans and cubical configurations vary throughout the building. If this is particularly onerous for your building, consider providing section plans for a representative sample of layouts and explaining the percent of regularly occupied spaces that these samples represent.

We have some vacant tenant spaces. How should I account for those when documenting this credit?

USGBC developed Reduced Occupancy Guidance for buildings that are 50% to 90% occupied (buildings under 50% occupied are not eligible for LEED-EBOM). This document gives the following guidance for IEQc2.4: “The credit performance threshold is based on the fully occupied and partially occupied portions of the building. Any spaces completely vacant or unused throughout the entire performance period make no contribution to the results and may be excluded.”

What qualifies as “regularly occupied spaces” for this credit? Does the total amount of regularly occupied space used for this credit have to match other credits?

Regularly occupied spaces are areas where people normally spend time either seated or standing as they work, study, or perform other focused activities in the building. Some common space types that are not considered regularly occupied space are corridors, bathrooms, storage, mechanical rooms, and break rooms. Conference/meeting rooms, classrooms, and hotel guest rooms are considered regularly occupied.

Why does the form calculate my high-albedo roof area, as a value greater than 100% of total roof area?

The form is calculating a weighted high-albedo area based on the solar reflectance index of the roofing material. So, a low-sloped roof with an SRI value of 100 has a higher weighted area than a roof with an SRI value of 85. Because the required SRI value is 78 for at least 75% of the roof area, if you have SRI value greater than 78 or if you have more than 75% of the roof covered with high-albedo materials, your weighted average can easily be more 100%.