Which baseline HVAC system do I use if my building has no heating or air conditioning?
Assign HVAC systems as per Appendix-G and Section 6 but set thermostatic setpoints out of range so that systems never turn on.
Assign HVAC systems as per Appendix-G and Section 6 but set thermostatic setpoints out of range so that systems never turn on.
The automated Trace 700 report provides less information than is requested by the Section 1.4 tables spreadsheet. The Section 1.4 tables spreadsheet must be completed.
Although there is no formal list of approved simulation tools, there are a few requirements per G2.2.1, including the ability of the program to provide hourly simulation for 8760 hours per year, and model ten or more thermal zones, which PHPP does not meet.
Use the building area method.
Submitting these forms is not common; however, it can be beneficial if you are applying for any exceptions.
For Section 9.4.1.1c, a manual control device would be sufficient to comply with mandatory provisions.
International projects are not required to enter a Target Finder score. Target Finder is based on U.S. energy use data.
Use the tables and definitions provided in 90.1 Appendix B to determine an equivalent ASHRAE climate zone.
The Energy Star portion of the form does not apply to international projects.
Any conditioned area must be included in the energy model.