Projects using the stream channel protection option need to also implement strategies to reduce the quantity of stormwater runoff, where possible. Typical strategies could include reduced building footprint, reduced hardscape, infiltration areas, or rainw

Projects using the stream channel protection option need to also implement strategies to reduce the quantity of stormwater runoff, where possible. Typical strategies could include reduced building footprint, reduced hardscape, infiltration areas, or rainwater harvest and reuse. These stategies need to be described in the stormwater management plan and narrative in order to meet the credit requirements.

The landscape architect provides LEED documentation for submittal to LEED Online. Provide landscape drawings.If installing irrigation, provide area, species factor, density factor, microclimate factor, project evapotranspiration rate, and irrigation type

The landscape architect provides LEED documentation for submittal to LEED Online.

Provide landscape drawings.
Provide the total water applied (both for the baseline and design case) and non-potable water supply.
If using non-potable water, provide information on source, and other documents that support proof of non-potable water use.
Write a narrative describing the landscape and irrigation installed, provide detail on the calculations used, and detail about the supply and availability of non-potable water used.

For WEc1.2: No Potable Water Use or No Irrigation, projects have to achieve a 50% reduction in total water applied in addition to eliminating irrigating with potable water. That is, even if a project uses non-potable water for irrigation, it must also red

For WEc1.2: No Potable Water Use or No Irrigation, projects have to achieve a 50% reduction in total water applied in addition to eliminating irrigating with potable water. That is, even if a project uses non-potable water for irrigation, it must also reduce the total water use for irrigation by 50%. To use non-potable water to pursue WEc1.2, projects must provide a detailed narrative on the actual source and available quantity of the non-potable water as well as the anticipated schedule for implementation of the non-potable system.

Fill out the LEED Submittal Template. You will need to provide information on the blackwater source (toilet or urinal), annual quantity treated, annual quantity infiltrated onsite, annual quantity reused onsite, and plumbing drawings or other documents th

Fill out the LEED Submittal Template. You will need to provide information on the blackwater source (toilet or urinal), annual quantity treated, annual quantity infiltrated onsite, annual quantity reused onsite, and plumbing drawings or other documents that detail information about the onsite treatment, infiltration, and reuse capabilities of your project.