Hi , I am working on a 100, 000 sqft office building with 50% of the spaces being storage which are served by MAU with gas heat, looking at the baseline system it comes with system 5 VAV with reheat , do i model these storage as system 5 and use the same cooling source that we have in baseline as in proposed or use some other system?

 

TIA 

 

Rajat

0

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Wed, 10/22/2025 - 22:12

Are the storage system heating only? If so you could model the baseline as a System 9 and the rest of the building as a system 5. 

Wed, 10/29/2025 - 09:57

Yes marcus they are heating only