ND-v4 NPDp3:Connected and open community

Internal Connectivity of a 3ha ND project. How to calculate?

Hi, All!
 

Dear Community, 

One of my current projects has a 3hectare territory (more than 5acre), and with all its characteristics goes under LEED ND (it has a "City-in-a-City" concept).

The credit required 54 intersections per sq km. 3 hectare is 0.03 sq km. Does this mean, that the required number of internal intersections is at least 2? It just looks strange as a requirement. 

Thank you.

0

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Sun, 04/06/2025 - 20:08

Marine, your calculation is correct: a 3 ha project site needs at least 2 internal intersections. Those intersections can be motorized-to-motorized, motor-to-non motor, or non mortor-to-non motor. Eliot

Mon, 04/07/2025 - 08:17

Thank you for the response, it really helped! 