Under Case 3, delete the text: "for a maximum of up to two points" from the third paragraph.

Delete bullet 2 and 4 from the Load Flexibility and Management Strategies

Under Step by Step Guidance, Replace Case 2 with the following:
"Case 2. Demand Response Capable Building
Refer to the LEED v4 reference guide, Case 2. Demand Response Program Not Available, with the following change:

Under the LEED v4.1 update, project eligibility for Case 2 is no longer restricted to applications where a demand response program is not available. However, the project team must still contact the utility service provider to discuss potential participation in a current or future DR program."

Revise language under Step 3 to read as:
"Implement one or both of the strategies identified during step 2.
Eligible strategies include peak load optimization achieved by reducing on-peak load by at least 10% compared to peak electrical demand, or installation of on-site thermal energy storage for heating and cooling and/or electricity storage capable of reducing on-peak load by at least 10% as compared to peak electrical demand. On-site storage enables the building to store energy and use it during peak demand times, increasing annual energy savings and reducing strain on the grid.

Under Further Explanation, delete the Load Flexibility and Management Strategies section

Revise Peak Demand Reduction section title to "On-site Thermal and/or Electricity Storage" and revise the paragraph under it to: "The reference case for demonstrating peak demand reduction via the On-site thermal and/or electricity storage strategy is the Proposed design from the Optimize Energy Performance energy model without the thermal and/or electricity storage strategy in place.

Delete the "Flexible Operating Scenarios" and "Grid Resilience Technologies" sections.

Revise the second sentence in the Single Strategy, Multiple Points section to read as: "For example, a set of demand reduction strategies used to achieve Case 2. Demand Response Capable Building may also meet the criteria for Case 3. Load Flexibility and Management Strategies for Peak Load Optimization.

Revise Exemplary Performance to read as: "Achieve Case 1 with the capability for at least a 20% peak demand savings, or achieve at least three points under Case 1 and Case 3, or achieve at least three points under Case 2 and Case 3."