Hello Marcus, 

I have unique scenario in which I believe the answer is 'No' but cannot find a definitive answer. 

My project contains 6 floors of parking and 12 floors of residential above it. Parking is owned by the city, residential is owned by the developer. 

Parking is pursuing Parksmart and Residential is pursuing LEED v4 NC.  

Parksmart is awarded points if included within the LEED Project Boundary. 

Was asked if the energy model of the parking could simply be combined with the energy model of the residential for the LEED application. I think the answer is no because the requirements of Table G3.1.1A Building HVAC System Types would not be adhered to. 

Is there a better explanation that I may be missing?

Thanks for your response - and for all your energy modeling expertise on this forum!

-dave