Does ADC have to be included in the overall waste total for Option 2 or is it just factor into the overall total for Option 1 only?
-If Option 2 is selection on the LEED Online form the ACD check box disappears.
Forum discussion
NC-v4.1 MRc5: Construction and Demolition Waste Management
Does ADC have to be included in the overall waste total for Option 2 or is it just factor into the overall total for Option 1 only?
-If Option 2 is selection on the LEED Online form the ACD check box disappears.
LEEDuser is supported by our premium members, not by advertisers.
Go premium forTo post a comment, you need to register for a LEEDuser Basic membership (free) or login to your existing profile.
Dave Hubka
Practice Leader - SustainabilityEUA
LEEDuser Expert
532 thumbs up
February 2, 2023 - 9:28 am
ADC must be included in waste calcs and is considered 'waste that went to the landfill'. It is not diverted from the landfill.