performance period date extension

We are submitting a v4 EB-OM project and need to know if the performance period for all credits ends on the same date and two (2) credits need to be extended to two weeks later - is that acceptable? 

All credits still end within 30 days of each other.

Example: Start date March 1 -  End Date May 31 : Two Credit extension end date June 15